e-Subscribe to Updates  e-Subscribe to updates

I-10 (Loop 1604 to South of Huebner Road)

According to the Texas Transportation Institute’s 2010 study, I-10 between Loop 1604 and Huebner Road is one of the most congested areas of San Antonio and one of the three most heavily trafficked segments of road in the San Antonio metro area. The $36 million expansion to relieve this congestion is under construction and on track for completion by summer 2014.

When construction is finished, the following improvements will help get you to your family quicker each day by increasing traffic flow and reducing congestion points.
  • Addition of at least one main lane in each direction
  • Elimination of a redundant west-bound on-ramp at the Huebner Oaks shopping center
  • Elimination of a redundant west-bound off-ramp at DeZavala
  • Addition of a turnaround at UTSA Boulevard for east-bound traffic

Project Progress

With about one-sixth of the project complete, progress is more noticeable to the causal observer. The work has included

  • Demolition of center concrete median barrier
  • Preparation for the expansion of main lanes between UTSA Boulevard and DeZavala
  • Preparation for the construction of the UTSA turnaround bridge
Contact Us

Josh Donat
(210) 615-5932

P.O Box 29928
4615 NW Loop 410
San Antonio, TX 78229-0928
E-mail