Shop Drawings - Proposed Web-Based Shop Plan Review
Discussions have begun on evolving the current e-mail-based
transmission process into a centralized web-based process.
The purpose of this conversion would be to:
- Guide fabricator submittal through auto-filling electronic
forms
- Provide for statewide shop drawing status/submittal access
via account specific internet and intranet rights
- Allow for District control of notification and access
preferences, reviewer assignments, among other features.

Description:
1. Account Creation -
All users outside of TxDOT and all TxDOT users with rights beyond
“view and print” must create an account with password:
- Accounts are sub-groups of District/Division office master
groups within TxDOT
- This hierarchy applies similarly to companies needing access
from outside of TxDOT
- Each master group will have an administrator
1a. District Validation
- The District assigns contacts and a reviewer to each
CSJ/Structure/Item;
- A link to DCIS will help fill in certain project information
when a CSJ is entered and found;
- Review item drop down lists will facilitate item-reviewer
association, or where appropriate, a district Admin might select
“All” from the list and simply assign all items to one reviewer,
“District” or “BRG” for example;
- A fabricator with a valid account can upload a submittal
before the District has provided this information, but the
submittal would remain grayed out (inaccessible) until it is
“validated” by the District
1b. Fabricator Initialization
- The Fabricator submits a drawing set either prior to
District validation, or after.
- Submitting before District validation generates an email to
the District contact cueing them to fill in other necessary
contact info to secondarily validate the submittal.
- Submitting after the District has input contact information
also generates a secondarily validated status.
2. Reviewer Notification
A secondarily validated submittal generates an email to the
reviewer soliciting concurrence with their assignment as reviewer:
- Clicking a link in the email takes them to the website where
they will accept or reject their reviewer status;
- Acceptance associates their account with that submittal,
enabling download and upload privileges;
- Rejection triggers an email to the District contact to
assign a new reviewer and the acceptance cycle is then repeated.
3. Begin Review
The assigned reviewer downloads the drawing file, annotates and
stamps it and uploads it back to the database.
4. Review Complete
- Uploading an “Approved” (“AP” or “AX”) drawing file to the
database via the web page triggers an email notification to the
Contractor, Fabricator and Detailing Office (where applicable),
and all pre-input District personnel (as associated by the
District Admin)
- The email to the Fabricator also instructs them to print a
paper set for the Construction Division Inspector to be made
available at the fabrication plant
- Uploading a “Returned for Correction” file generates an
email to the Fabricator, and, or Detailing Office only, and the
submittal/review cycle would repeat
- The current status and history of the submittal would be
available on the web page for TxDOT and account specific
non-TxDOT entities to see.
5. Archiving
When a project is complete, the District
Admin uploads all additional “as-built”
files to the database, checking off any
database shop drawings that are superseded
thereby, and changes the status of the CSJ
and all associated documents to “Finaled”,
triggering an email notification to GSD
informing them of the availability of the
files (or accomplished by an automated
transfer at project end);
Upon downloading by GSD- a database
calendar clock is started, at the end of
which time (pre-determined amount - Ex: 1
year) the drawing files are purged to a
“trash” bin (temp storage) and only the
status history remains via the web site;
trash bin items are emptied after another
amount of preset time.